HAPTER 1: INTRODUCTION 1. Which of the following is true about a project? A)It is a temporary endeavor undertaken to create a unique product, process, or service. B)It is an ongoing endeavor...


HAPTER 1: INTRODUCTION

1.

Which of the following is true

about a project?

A)It is a temporary endeavor undertaken

to create a unique product, process, or service.

B)It is an ongoing endeavor undertaken

to create and retire a unique product, process, or service.

C)It is a temporary endeavor undertaken

to create a temporary product, process, or service.

D)It is a unique endeavor undertaken to

create a temporary product, process, or service.

E)None of the Above

2.

Which of the following

describe a project? (Select all that apply):

A)A Business Problem

B)A Business Solution

C)An entity that operates in a static

environment

D)An entity that operates in a changing

environment

E)Answers B and D Only

3.

What is an operation?

A)Routine work by people in their

day-to-day jobs

B)Covert work by an undercover team

C)Work by a surgeon

D)The job of a computer operator

E)None of the Above

4.

The classic theory of triple

constraint refers to (Select all that apply):

A)Scope

B)Schedule

C)Cost

D)Quality

E)Answers A, B and C Only

5.

Project constraints as defined

within the PPA concept include (Select all that apply):

A)Scope

B)Schedule

C)Cost

D)Quality

E)All of the Above

6.

The output from project

execution can be:

A)A Product

B)A Process

C)A Product or a Process

D)A Highly Skilled Team

E)None of the Above

7.

Which of the following best

describes project management?

A)A state-of-the art software tool used

to manage a project to success

B)The art and science of effectively and

efficiently converting an idea into a viable software product

C)The art and science of effectively and

efficiently converting an idea into a viable product or process

D)The art and science of effectively and

efficiently converting an idea into a viable product or process through the use

of a project management tool

E)None of the Above

8.

The PPA consists of:

A)Six Stages

B)Five Stages

C)33 Steps

D)31 Steps

E)Answers A and C Only

9.

Stage gates in the PPA are

designed to assess:

A)Go decision

B)No Go decision

C)Go/ No Go decision

D)Go Back decision

E)None of the Above

10.

At a specific stage gate of a

project, the sponsor can (Select all that apply):

A)Open the stage gate and lets the team

proceed

B)Direct the team to rework certain

deficient area

C)Decide to initiate the project

suspension process

D)Ask the project office regarding the

current policies regarding the stage gate actions

E)Answers A, B and C Only

11.

Of the following, which PPA

stage typically consumes most time of the project team?

A)Idea

B)Pre-Launch

C)Launch

D)Execute

E)None of the Above

12.

Within the context of this

test, PMI stands for:

A)Presidential Management Intern

B)Pension Management Institute

C)Plumbing Manufacturers Institute

D)Project Management Institute

E)None of the Above

13.

Which of the following is the

correct definition of the term PMBOK®?

A)The evening hop of the African

Springbok

B)The evening walk of the Springbok

Scottish Terrier

C)Project management body of knowledge

D)The evening socials at the Springbok

club (NY/NJ)

E)None of the Above

14.

Which of the following is not

correct about the PMBOK®?

A)It consists of five processes groups

B)It consists of nine knowledge segment

groups

C)A given project plan consist of

information based on the nine knowledge groups

D)It specifically describes how to

execute the various steps needed to manage a project from start to finish.

E)None of the Above

15.

PMI provides certification

examinations for:

A)A. Certified Associates in Project

Management (CAPM™)

B)B. Project Management Professional

(PMP®)

C)C. IT Project+

D)D. CMMI

E)E. Answers A and B Only

16.

CompTIA® provides

certification examinations for:

A)Certified Associates in Project

Management (CAPM™)

B)Project Management Professional (PMP®)

C)IT Project+

D)CMMI

E)None of the Above

17.

Which of the following

statements is not correct?

A)Project development methodology is the

same as a system development methodology.

B)Project management methodology deals

with the processes and steps to manage a project.

C)System development methodology deals

with the steps to develop a system.

D)Product development methodology deals

with the steps to develop a product.

E)None of the Above

18.

Which of the following does

not qualify as software development methodology?

A)Joint Application Design (JAD)

B)Rapid application Design (RAD)

C)Rational Unified Process (RUP)

D)Project Process Architecture (PPA)

E)None of the Above

CHAPTER 2: FUNDAMENTALS

19.

The most appropriate tool for

decomposing high level items into lower level items is:

A)Histogram

B)Delphi

C)WBS

D)PERT Chart

E)None of the Above

20.

Which of the following is not

a component of a WBS?

A)Phases

B)Deliverables

C)Tasks

D)Stakeholders

E)None of the Above

21.

Project phase names can be:

A)Nouns

B)Verbs

C)Nouns or verbs

D)Adjectives

E)None of the Above

22.

Deliverable names:

A)Can be nouns

B)Can be verbs

C)Should be nouns

D)Should be verbs

E)None of the Above

23.

It is recommended that

deliverables be:

A)Longer than 20 days in duration

B)20 days or less in duration

C)20 days in duration

D)Depends on the size of the project;

the larger the project, the longer the duration of a deliverable

E)None of the Above

24.

For a deliverable to be well

defined, it should (Select all that apply):

A)Have at least one paragraph of

detailed description

B)Have clearly defined completion

criteria

C)Have a clearly defined owner

D)Be mandatory

E)Answers B and C Only

25.

Within a project schedule, a

milestone should appear:

A)At the end of every deliverable

B)At the start of every deliverable

C)Every eight days or less

D)Every ten days or less

E)None of the Above

26.

Which of the following

statements is not true?

A)The WBS identifies the project

elements that will need resources and thus is the primary input to resource

planning.

B)The WBS will be used to ensure that

all identified work has been estimated.

C)The WBS elements provide a progressive

breakdown from the big picture to smaller project elements.

D)The WBS elements will be used to

perform resource leveling to compress the project schedule.

E)None of the Above

27.

You are going to begin to plan

the resources for your project. In order to develop a comprehensive list of

people, equipment, and materials, the key input to the process is the

project’s:

A)WBS

B)Responsibility assignment matrix

C)Expert judgment

D)Project charter

E)None of the Above

28.

Top-down approach of WBS

decomposition means:

A)Identifying specific activities

related to the project at the lowest level and then aggregating and organizing

them into higher levels

B)Identifying specific activities

related to the project at the highest level and then decomposing them into

successive lower levels

C)Having the more senior team members

decompose the higher level while junior team members decompose the lower levels

D)Decomposing only the top-level project

scope elements downwards

E)None of the Above

29.

An element inherently missing

from a WBS is:

A)Work Package

B)Tasks

C)Specific logical order of elements

D)Resources

E)None of the Above

30.

The various components of a

WBS can be assigned numbers in order to (select all that apply):

A)A. Define the parent and child

relationship among different levels of the WBS

B)B. Assign a unique identification to

each element of the WBS

C)C. Assign the order of execution of

various WBS elements

D)D. Provide traceability of

deliverables and tasks to specific requirements

E)E. Answers A, B and D Only

31.

Given a network of tasks, in

order to determine the length of time it would take to finish the work requires

that one computes the network’s:

A)Critical Length

B)Critical Path

C)Critical Chain

D)Critical Effort

E)None of the Above

CHAPTER 3: IDEA STAGE

32.

The primary purpose of the

Idea stage is to:

A)Filter ongoing projects to reduce

scope

B)Filter approved projects to reduce

schedule

C)Filter ideas to separate viable ideas

from half-baked ideas

D)Filter ideas to reduce the number of

ideas

E)None of the Above

33.

Value-to-Business of a project

is best defined by:

A)The project manager as he/she has

experience with such information

B)A subject matter expert (SME) with

knowledge of the business value

C)Chief financial officer

D)The business area proposing the

project

E)Answers A and B Only

34.

Project stakeholders can be

classified into (select all that apply):

A)Policy level

B)Budget level

C)Implementation level

D)Schedule level

E)Answers A and C Only

35.

When developing a Project

Request, which of the following should not be included?

A)Value-to-Business

B)Specific solution to the problem

C)Assumptions

D)Estimates of cost and delivery

schedule

E)Answers B and D Only

36.

The person with the

responsibility to complete the project successfully is:

A)The sponsor

B)The program manager

C)The project manager

D)The team

E)Answers A and C Only

37.

You have recently been hired

as a project manager. During your orientation with the manager of the project

office you learn that the project selection is primarily the responsibility of

management. Which of the following is your best action?

A)You don’t need to be concerned about

the project selection method of your new organization as that is not your

responsibility.

B)You need to be concerned about the

project selection method of your new organization only if you plan to move into

general management position.

C)You should learn about the project

selection method of your new organization.

D)You should avoid anything to do with

project selection method as it is typically fraught with corporate politics.

E)None of the Above

38.

You are in the initiation

phase of your project and ask the team members to be sure to document all

assumptions. One of the team members is not so keen on spending the time for

this activity. His explanation is that assumptions can change and he will be

required to spend more time in documentation activity. What would be your

response?

A)A. In case of schedule and/or cost

overrun, the team will have specific data to explain away such variances.

B)B. Assumptions generally involve a degree

of risk and need to be tracked.

C)C. Assumptions limit the project

team’s options.

D)D. Report the team member to the

appropriate functional manager as the team member is not following your orders.

E)E. None of the Above

39.

At the end of the Idea stage,

there is:

A)No stage gate review, as it is too

early in the project

B)One stage gate review

C)A stage gate review only if the

project office requests it

D)All of the Above

E)None of the above

40.

The stage gate review at the

end of the Idea stage:

A)Is necessary only if the work on the

Idea stage step was substandard

B)Is necessary only if the people doing

the work are new to the organization

C)Is necessary for all projects

D)Is carried out only if the sponsor has

the time

E)None of the Above

OPM3 – CHAPTERS 1 AND 2

Kapurs Center for Project Management

– PPA Model for Success and Capability Maturity Model (CMM)

Please reference OPM3, Chapters 1 and 2 text material.

41.

OPM3 is designed to provide a

wide range of benefits to organizations, senior management, and those engaged

in project management activities. OPM3…

A)Strengthens the link between strategic

planning and execution, so project outcomes are predictable, reliable, and

consistent, and correlate with organizational success.

B)Identifies the Best Practices which

support the implementation or organizational strategy through successful

projects

C)Identifies the specific Capabilities

which make up the Best Practices, and the dependencies among these Capabilities

and Best Practices

D)Places Best Practices and Capabilities

within the context of not only Project Management, but also Program Management

and Portfolio Management processes

E)All of the Above

42.

Organizational project

management is the systematic management of projects, programs and portfolios in

alignment with the achievement of strategic goals.

A)True

B)False

43.

OPM3 is an acronym for the

Organizational Project Management Maturity Model – a standard developed under

the stewardship of the Project Management Institute.

A)True

B)False

44.

OPM3 also helps organizations

wishing to increase their organizational project management maturity to plan

for improvement.

A)True

B)False

45.

OPM3 provides a way to advance

an organization’s strategic goals through the application of project management

principles and practices.

A)True

B)False

46.

Maturity assessment forms a

basis for deciding whether or not to pursue improvements in specific critical

areas, such as the domains of Portfolio, Program, or Project Management.

A)True

B)False

47.

The scope of OPM3 is global.

A)True

B)False

48.

Depending on the

organization’s size, complexity, and sophistication, it may initiate or manage

multiple and interacting projects simultaneously.

A)True

B)False

49.

A Portfolio is a collection of

projects and/or programs and other work that are grouped together to facilitate

effective management of that work to meet strategic objectives.

A)True

B)False

50.

It may be helpful for the user

to think of OPM3 as consisting of three interlocking elements: Knowledge, Assessment,

and Improvement.

A)True

B)False

51.

In the Knowledge element, the

user becomes proficient with OPM3, to be comfortable with the body of Best

Practices knowledge it contains, with the idea of organizational project

management, with organizational project management maturity, and with the

concept and methodology of OPM3.

A)True

B)False

52.

In the Assessment element, the

organization is compared to OPM3 to determine its current location on a

continuum of organizational project management maturity.

A)True

B)False

53.

In the improvement element,

organizations that decide to move ahead with change initiatives leading to

increased maturity can use the results of the assessment as a basis for

planning, and move forward to implement the plan.

A)True

B)False

54.

The first step (Knowledge

element) is for the organization to prepare for the process of assessing its

organizational project management maturity in relation to OPM3.

A)True

B)False

55.

For those organizations

choosing to pursue organizational improvements leading to increased maturity,

the results of the previous step (step 2) will form the basis for an

improvement plan.

A)True

B)False

56.

The documentation of which

Capabilities the organization does and does not have – including the

dependencies among them – permits a ranking of needed Capabilities and Outcomes

according to their priority for the organization.

A)True

B)False

May 15, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here