Replacement Project for Darling Harbour Swing Bridge – Tender Documentation
Replacement Project for Darling Harbour Swing Bridge – Tender Documentation
Statement of Work
The overall scope of work shall encompass the replacement of Darling Harbour Swing Bridge and the same shall comprise the replacement of the superstructure, replacement of the swing span, modifications with respect to substructure, overall mechanical as well as electrical overhaul, replacement of the operator house as well as the replacement of fender system. The overall work shall be delivered within a budget of AUD 32.474 Million and in the period between 11th September 2018 and 05th December 2018. The other important consideration concerning this project shall be the minimisation of construction impacts for public with all of the replacements concerning superstructure as well as swing span shall be undertaken during the ten day closure period of the bridge.
Work Breakdown Structure
The work breakdown structure (“WBS”) on the basis of the statement of work is presented as follows –
Table 1 – WBS
WBS ID #
Level 0
Level 1
Level 2
1
Replacement Project for Darling Harbour Swing Bridge
1.1
Project Plan & Set-up Stage
1.1.1
Development of Project Charter, Project Authorities / leaders, etc.
1.1.2
Project Team Identification, Recruitment / Assignment & Setup
1.1.3
Project Schedule Planning
1.1.4
Project Budget Planning
1.1.5
Project Risk Planning
1.1.6
Project Related Processes Planning
1.1.7
Project Management Plan - Integration & Documentation
1.2
Site Review, Resource Availability Review & Documentation
1.2.1
Preliminary Feasibility Assessment & Review
1.2.2
Discussions, Project Team Brainstorming & Planning for Site Review
1.2.3
Undertaking Site Review
1.2.4
Site Review Consultations
1.2.5
Documentation of the Site Review Identifications
1.2.6
Validation / Assessment of the People & Materials Resource Available for the Project
1.2.7
Resource Review Project Team Discussions
1.2.8
Site Review Documentation Approvals
1.2.9
Review, Approvals & Finalization
1.3
Project Resource for Construction Activities - Review & Planning
1.3.1
Assessments, Review & Discussions for the Project Resources Requirement
1.3.2
Determination of the Resources Required and the Allocation related Planning
1.3.3
Identification of External Material Resources Required
1.3.4
Procurement / Acquisition Strategy Identification
1.3.5
Procurement / Acquisition Plan Development
1.3.6
Implementation Plan Review & Assessment
1.3.7
Implementation Plan Finalization
1.3.8
Review, Approvals & Finalization
1.4
Procurement
1.4.1
Grouping and Classification of the Various Material Resources Required
1.4.2
Design and Issuance of Request for Proposal for Procurement of each of the Materials
1.4.3
Receipt of the Quote from various vendors, suppliers, etc. & review, assessment, closure / finalization as well as contract signing with the vendors / suppliers
1.4.4
Payments Planning and Releasing of Payments as per Contracts
1.4.5
Receipt of the Contracted Materials in the Site / Facility of the Project
1.6
Construction Design - Replacement of Superstructure
1.6.1
Site Review Findings Assessment
1.6.2
Design Guidance Development
1.6.3
Overall Designing
1.6.4
Design Review
1.6.5
Discussions, Revisions & Re-review
1.6.6
Design Finalization
1.6.7
Review, Approvals & Finalization
1.7
Construction Design - Replacement of Swing Span
1.7.1
Site Review Findings Assessment
1.7.2
Design Guidance Development
1.7.3
Overall Designing
1.7.4
Design Review
1.7.5
Discussions, Revisions & Re-review
1.7.6
Design Finalization
1.7.7
Review, Approvals & Finalization
1.8
Construction Design - Modifications to Sub-structure
1.8.1
Site Review Findings Assessment
1.8.2
Design Guidance Development
1.8.3
Overall Designing
1.8.4
Design Review
1.8.5
Discussions, Revisions & Re-review
1.8.6
Design Finalization
1.8.7
Review, Approvals & Finalization
1.9
Construction Design - Complete Overhaul of Mechanical & Electrical Aspects
1.9.1
Site Review Findings Assessment
1.9.2
Design Guidance Development
1.9.3
Overall Designing
1.9.4
Design Review
1.9.5
Discussions, Revisions & Re-review
1.9.6
Design Finalization
1.9.7
Review, Approvals & Finalization
1.10
Construction Design - Replacement of Operator House
1.10.1
Site Review Findings Assessment
1.10.2
Design Guidance Development
1.10.3
Overall Designing
1.10.4
Design Review
1.10.5
Discussions, Revisions & Re-review
1.10.6
Design Finalization
1.10.7
Review, Approvals & Finalization
1.11
Construction Design - Replacement of Fender System
1.11.1
Site Review Findings Assessment
1.11.2
Design Guidance Development
1.11.3
Overall Designing
1.11.4
Design Review
1.11.5
Discussions, Revisions & Re-review
1.11.6
Design Finalization
1.11.7
Review, Approvals & Finalization
1.12
Construction Implementation - Replacement of Superstructure
1.12.1
Site Review for Pre-Implementation Assessment
1.12.2
Team Resource Deployment
1.12.3
Material Resource Deployment
1.12.4
Review of Finalized Design
1.12.5
Construction Work Undertaking
1.12.6
Review Post Completion
1.12.7
Review, Approvals & Finalization
1.13
Construction Implementation - Replacement of Swing Span
1.13.1
Site Review for Pre-Implementation Assessment
1.13.2
Team Resource Deployment
1.13.3
Material Resource Deployment
1.13.4
Review of Finalized Design
1.13.5
Construction Work Undertaking
1.13.6
Review Post Completion
1.13.7
Review, Approvals & Finalization
1.14
Construction Implementation - Modifications to Sub-structure
1.14.1
Site Review for Pre-Implementation Assessment
1.14.2
Team Resource Deployment
1.14.3
Material Resource Deployment
1.14.4
Review of Finalized Design
1.14.5
Construction Work Undertaking
1.14.6
Review Post Completion
1.14.7
Review, Approvals & Finalization
1.15
Construction Implementation - Complete Overhaul of Mechanical & Electrical Aspects
1.15.1
Site Review for Pre-Implementation Assessment
1.15.2
Team Resource Deployment
1.15.3
Material Resource Deployment
1.15.4
Review of Finalized Design
1.15.5
Construction Work Undertaking
1.15.6
Review Post Completion
1.15.7
Review, Approvals & Finalization
1.16
Construction Implementation - Replacement of Operator House
1.16.1
Site Review for Pre-Implementation Assessment
1.16.2
Team Resource Deployment
1.16.3
Material Resource Deployment
1.16.4
Review of Finalized Design
1.16.5
Construction Work Undertaking
1.16.6
Review Post Completion
1.16.7
Review, Approvals & Finalization
1.17
Construction Implementation - Replacement of Fender System
1.17.1
Site Review for Pre-Implementation Assessment
1.17.2
Team Resource Deployment
1.17.3
Material Resource Deployment
1.17.4
Review of Finalized Design
1.17.5
Construction Work Undertaking
1.17.6
Review Post Completion
1.17.7
Review, Approvals & Finalization
1.18
Transition and the Post Construction Activities
1.18.1
Testing of the Overall Structure and Infrastructure & regulatory Review
1.18.2
Overall Integration, Practical Use Deployment as well as Evaluations for Roll-out
1.18.3
External Approvals As Applicable
1.18.4
Review, Approvals & Finalization
1.19
Project Closure Phase
1.19.1
Evaluation of the Construction Outcomes against Contract Terms
1.19.2
Lessons Learnt related Project Documentation
1.19.3
Sign-Off on Project Completion
1.19.4
Roll-out
Milestone schedule
The milestones for the project is stated as follows –
Table 2 – Milestone Schedule
S. No.
Milestone
Start Date
End Date
1
Project Plan & Set-up Completion
18-Sep-18
18-Sep-18
2
Site Review Completion
26-Sep-18
26-Sep-18
3
Resource Planning
30-Sep-18
30-Sep-18
4
Procurement
15-Oct-18
15-Oct-18
5
Construction Design Completion
05-Nov-18
05-Nov-18
6
Construction Implementation - Replacement of Superstructure & Swing Span & Modifications to Sub-structure
16-Nov-18
16-Nov-18
7
Construction Implementation - Complete Overhaul of Mechanical & Electrical Aspects, Replacement of Operator House, and, Replacement of Fender System
25-Nov-18
25-Nov-18
8
Post Construction Activities
02-Nov-18
02-Nov-18
9
Project Closure
02-Nov-18
02-Nov-18
The milestone schedule above is undertaken on the basis of the project schedule presented as follows –
Table 3 – Project Schedule
WBS ID #
Project Tasks
Start Date
End Date
1
Replacement Project for Darling Harbour Swing Bridge
11-Sep-18
05-Dec-18
1.1
Project Plan & Set-up Stage
11-Sep-18
18-Sep-18
1.2
Site Review, Resource Availability Review &...