Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at...



Given the following information for a one-year project, answer the following questions. Recall


that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the


budget at completion.


PV ¼ $23,000


EV ¼ $20,000


AC ¼ $25,000


BAC ¼ $120,000


a. What is the cost variance, schedule variance, cost performance index (CPI), and


schedule performance index (SPI) for the project?


b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget


or over budget?


c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project


performing better or worse than planned?


d. Use the SPI to estimate how long it will take to finish this project.


e. Sketch the earned value chart for this project, using Figure 7-5 as a guide.



May 20, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here