Given the due dates in the previous problem, how would you maximize the number of projects completed on time? (The difference here is that you are ignoring revenues.) Use a two-way data table to see...


Given the due dates in the previous problem, how would you maximize the number of projects completed on time? (The difference here is that you are ignoring revenues.)


Use a two-way data table to see how sensitive the project completion time in the LAN project is to the duration of activities E and H (selecting cables and wiring offices). Let the durations of these activities vary from 3 to 6 days and from 10 to 16 days, respectively, in increments of 1 day each.



May 22, 2022