Plz solve this question of civil project management
Extracted text: From the following table, develop network diagram, determine the critical path, and Calculate the minimum duration of project completion. Activity Predecessor Duration A В A 4 C A 3 D В E В 4 F C 6. G D,F 4 H E I F 4 J G,H,I 2