For the purpose of transparency, when does Scrum say a new increment of working software must be available?   A. After the acceptance testing phase.  B. Before the release Sprint.   C. Every 3...


For the purpose of transparency, when does Scrum say a new increment of working software must


be available?   A. After the acceptance testing phase.  B. Before the release Sprint.   C. Every 3 Sprints.                 D. At the end of every Sprint.   E. When the Product Owner asks to create one.