Extracted text: For the given construction project: 1. Draw the Precedence Diagram 2. Calculate the forward and backward passes 3. Highlight the Critical Path No. Activity Duration Predecssors Relationship Lag 1 Mobilize 1 2 Clearing & Grubbing 3 Layout Fence Alignment 1 2 4 Deliver Posts to Site 3 SS 1 5 Auger Post Holes 7 4 SS 2 6 Set Posts in Holes 7 SS 7 Backfill and Plumb Posts 10 6. SS 1 8 Install Boards for Fence 5 7 FF 1 9 Deliver Boards for Fence 3 8 SF 7 10 Paint Boards 12 8 SS 11 Plant Shrubs Along Fence 7 10 SS 8 12 Final Inspection 1 8, 10*, 11 |(10*)/2 13 Demobilize 1 12 3.