Extracted text: For the activity below, fill in the table. Comment on the status of the activity in terms of budget and schedule. Activity 1: 240 Footings Duration: 3 months Start Date: 6 months from project start Total Cost: $2,400,000 Update Time: 7 months from project start Spent: $840,000 Footings Completed: 60 Footings formed, 24 Footings formed and reinforced 12 Footings formed, reinforced and poured Estimate ACWP BCWP BCWS To Complete At Completion Cost Variance Schedule Variance Status