First Printing and Copy Center has 4 jobs to be scheduled chapter. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Job A was scheduled to begin early on day 2 and to...


First Printing and Copy Center has 4 jobs to be scheduled chapter. Production scheduling personnel are

reviewing the Gantt chart at the end of day 4. Job A was scheduled to begin early on day 2 and to end on the

middle of day 9. As of now (the review point after day 4), it is 2 days ahead of schedule. Job B should begin

on day 1 and end on day 3. It is on time. Job C was to begin on day 3, but maintenance forced a delay of 1½

days. The job should now take 5 full days. It is now on schedule. Job D is a day behind schedule. It started at

the beginning of day 2 and should require 6 days to complete. Develop a Gantt schedule chart for First

Printing and Copy Center.