EVM Calculation Calculate the PV, EV, CV, SV, CPI and SPI 1. Duration 2. Budget 3. for the following scenario at 2 months, 4 months, 6 months, 8 months and 10 months = 10 months = 500,000 % of work...




EVM Calculation
Calculate the

PV, EV, CV, SV, CPI and SPI
1.
Duration
2.
Budget
3.



for the following scenario at 2 months, 4 months, 6 months, 8 months and 10 months



= 10 months



= 500,000



% of work expected to be completed
= 5% at 2 months; 35% of 4 months; 50% at 6 months; 70% at 8 months and 100% at 10 months


4.% of work actually completed
= 0% at 2 months; 30% at 4 months; 60% at 6 months; 75% at 8 months and 100% at 10 months



Actual Cost
= 100,000 at the end of 2 months; 300,000 at the end of 4 months; 350,000 at the end of 6 months; 480,000 at the end of 8 months and 600,000 at the end of 10 months.