EVM CalculationCalculate thePV, EV, CV, SV, CPI and SPI1.Duration2.Budget3.
for the following scenario at 2 months, 4 months, 6 months, 8 months and 10 months
= 10 months
= 500,000
% of work expected to be completed= 5% at 2 months; 35% of 4 months; 50% at 6 months; 70% at 8 months and 100% at 10 months
4.% of work actually completed= 0% at 2 months; 30% at 4 months; 60% at 6 months; 75% at 8 months and 100% at 10 months
Actual Cost= 100,000 at the end of 2 months; 300,000 at the end of 4 months; 350,000 at the end of 6 months; 480,000 at the end of 8 months and 600,000 at the end of 10 months.