End item P is composed of three subassemblies: K,L, and W,K is assembled using 3 Gs and 4 Hs and 200 Hs Scheduled receipts are 10 Ks at the start of week 3, 30Ks at the start of week 6, and 200 Ws at...


End item P is composed of three subassemblies: K,L, and W,K is assembled using 3 Gs and 4 Hs and 200 Hs Scheduled receipts are 10 Ks at the start of week 3, 30Ks at the start of week 6, and 200 Ws at the start of week 3.



One hundred Ps will be shipped at the start of week 6, and another 100 at the start of week 7. Lead items are two weeks for subassemblies and one week for components G, H, and M. final assembly of P order size size for H is 200 units. Develop each of the following:


a. A product structure tree


b. An assembly time chart


c. A master schedule for P


d. A material requirement plan for K, G, and H.