During which project management process are risk and stakeholder’s ability to influence project outcomes the highest at the beginning of the process? A. Planning B. Executing C. Initiating D....


During which project management process are risk and stakeholder’s ability to influence project outcomes the highest at the beginning of the process?


A. Planning


B. Executing


C. Initiating


D. Monitoring and Controlling


You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in?


A. Planning


B. Executing


C. Initiating


D. Monitoring and Controlling