Draw a neat network diagram and find the critical path for the given activity table for software development.
Activity
Description
Predecessor
Duration
A
Analysis
None
2
B
Development
6
C
Testing
4
D
Documentation
3
E
Training
5
F
Implementation
G
Maintenance
B, D, E
a) Draw a neat network diagram and find LS,LF,ES,EF and mark appropriate Activity on Node.
b) Find the completion time of the project.
c) Find critical path. (calculation of ES, EF, LS, LF)