Draw a neat network diagram and find the critical path for the given activity table for software development. Activity Description Predecessor Duration A Analysis None 2 B Development None 6 C Testing...


Draw a neat network diagram and find the critical path for the given activity table for software development.























































Activity




Description




Predecessor




Duration



A



Analysis



None



2



B



Development



None



6



C



Testing



None



4



D



Documentation



A



3



E



Training



C



5



F



Implementation



A



4



G



Maintenance



B, D, E



2




a)    Draw a neat network diagram and find LS,LF,ES,EF and mark appropriate Activity on Node.


b)    Find the completion time of the project.


c)    Find critical path. (calculation of ES, EF, LS, LF)