Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available: Quantity of direct labor used...


Direct Labor Variances


Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available:

























Quantity of direct labor used590 hrs.
Actual rate for direct labor$12.50 per hr.
Bicycles completed in October280 bicycles
Standard direct labor per bicycle2 hrs.
Standard rate for direct labor$12.80 per hr.


a.Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.




















Direct Labor Rate Variance
Direct Labor Time Variance

Total Direct Labor Cost Variance



b.How much direct labor should be debited to Work in Process?