Diggitt Construction Company was the low bidder on a well-digging job for the Village of Drytown. On April 15, Diggitt signed a contract with Drytown for the job at a price of $40,000. At the same time, pursuant to the notice of bidding, Diggitt prevailed upon Ace Surety Company to execute a performance bond indemnifying Drytown on the contract. On May 1, after Diggitt had put in three days on the job, the president of the company refigured his bid and realized that if his company were to complete the job it, would lose $10,000. Accordingly, Diggitt notified Drytown that it was canceling the contract, effective immediately. What are the rights and duties of Ace Surety Company?