Dawson Toys Ltd produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy:
Direct materials: 6 microns per toy at £ 0.50 per micronDirect labour: 1.3 hours per toy at £ 8 per hourDuring July, the company produced 3,000 Maze toys. Production data for the month on the toy follow:
Direct materials: 25,000 microns were purchased for use in production ata cost of £ 0.48 per micronSome 5,000 of these microns were still in I at the end of the monthDirect labour: 4,000 direct labour-hours were worked at a cost of £ 36,000
Required(a) Compute the following variances for July:i. Direct materials price and quantity variances.ii. Direct labour rate and efficiency variances.(b) Prepare a brief explanation of the significance and possible causes of eachvariance.(c) What is meant by the term management by exception?