Extracted text: CS Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below: Billings on Contract Site Contract Cost Estimated Costs to Complete Collections on Price Incurred 3,750,000 1,000,000 Billings 5,000,000 900,000 1,000,000 1 5,000,000 5,000,000 900,000 2 7.000,000 2.500.000 4,000,000 3 1.000,000 1,000,000 1.500,000 1. If the company recoeds revenue over time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 31? A. 5,500,000 B. S00,000 C 250,000 D. 100,000 2. If the company records revenue at a point in time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 317 A. 5,100,000 8. S00,000 C 250,000 D. 100,000