Consider the (simplified) list of activities and predecessors that are involved in building a house (Table). Immediate Duration Activity Description Predecessors (Days) A Build foundation — 5 B Build...

1 answer below »

View more »
Answered Same DayDec 24, 2021

Answer To: Consider the (simplified) list of activities and predecessors that are involved in building a house...

Robert answered on Dec 24 2021
128 Votes
Solution
Consider the (simplified) list of activities and predecessors that are involved in building a house, as listed in Table 1.
    Activity
    Description
    Predecessors
    Duration (days)
    Activity A
    Build foundation

    —
    5
    Activity B
    Build walls and ceilings
    A
    8
    Activity C
    Build roof
    B
    10
    Activity D
    Do electrical wiring
    B
    5
    Activity E
    Put in windows
    B
    4
    Activity F
    Put on siding
    E
    6
    Activity G
    Paint house
    C, F
    3
Table 1: House-Building Activities
a. Draw a project network and use LP to find the critical path and the minimum number of days needed to build the house.
Here is one possible network diagram (an activity-on-arc diagram). The arrows (arcs) represent activities; the balls (nodes) have been numbered for ease of discussion:
1
0
Start
4
3
2
A
5
B
8
C
10
E
4
D
5
G
3
F
6
5
End
Managerial Formulation
Decision Variables
We are trying to decide when to begin and end each of the activities.
Objective
Minimize the total time to complete the project.
Constraints
Each activity has a fixed duration.
There are precedence relationships among the activities.
We cannot go backwards in time.
Mathematical Formulation
This is an example of a type of project-scheduling problem that can be solved with the Critical Path Method (CPM). These problems can be solved by hand, or with any of a large number of project management software packages. They can also be solved using linear programming, as is demonstrated here.
Decision Variables
Define the nodes to be discrete events. In other words, they occur at one exact point in time. Our decision variables will be these points in time.
Define ti to be the time at which node i occurs, and at which time all activities preceding node i have been completed.
Define t0 to be zero.
Objective
Minimize t5.
Constraints
There is really one basic type of constraint. For each activity x, let the time of its starting node be represented by tjx and the time of its ending node be represented by tkx. Let the duration of activity x be represented as dx.
For every activity x,
x
jx
kx
d
t
t
³
-
For every node i,
0
³
i
t

Solution Methodology
Here’s the spreadsheet...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30