Consider the project diagram in Figure 42.
This project must be completed in 90 days. The time required to complete each activity can be reduced by up to five days at the costs given in Table.
Cost of Reducing Activities Duration
Activity
by 1 Day ($)
A
300
B
200
C
350
D
260
E
320
Formulate an LP whose solution will enable us to minimize the cost of completing the project in 90 days.