Consider the merchandising problem faced by Nickledime Studios in problem 13. At present, the studio can only allocate $8 million to the merchandising project.  a. Write the linear program that models...


Consider the merchandising problem faced by Nickledime Studios in problem 13. At present, the studio can only allocate $8 million to the merchandising project.


 a. Write the linear program that models this situation.


b. What is the minimal completion time of the project, given this budgetary constraint?


a. Write the linear program that models this situation.


b. Determine a minimum cost schedule to complete the project within 16 weeks.