Consider the following project network, with task duration data provided: A 3 B 6 START D 3 E 2 FINISH 2 H 3 F 4 G 2 Which of the following is the completion time for this project? O a. 11 days Ob.9...


Consider the following project network, with task duration data provided:<br>A<br>3<br>B<br>6<br>START<br>D<br>3<br>E<br>2<br>FINISH<br>2<br>H<br>3<br>F<br>4<br>G<br>2<br>Which of the following is the completion time for this project?<br>O a. 11 days<br>Ob.9 days<br>Oc. 10 days<br>d. 12 days<br>Oe. 13 days<br>

Extracted text: Consider the following project network, with task duration data provided: A 3 B 6 START D 3 E 2 FINISH 2 H 3 F 4 G 2 Which of the following is the completion time for this project? O a. 11 days Ob.9 days Oc. 10 days d. 12 days Oe. 13 days