Consider Table 6-2, Network Diagram Data for a Small Project.Allduration estimates or estimates times are in days, and the network proceedsfrom Node 1 to Node 9.(Please answer the questions for...

1 answer below »
Consider Table 6-2, Network Diagram Data for a Small Project.All duration estimates or estimates times are in days, and the network proceeds from Node 1 to Node 9.(Please answer the questions for Chapter 6, number 2 under Exercises, pp 246.)














































































ACTIVITYINITIAL NODEFINAL NODEESTIMATED DURATION
A122
B232
C243
D254
E362
F463
G576
H682
I675
J781
K892


Answered Same DayDec 22, 2021

Answer To: Consider Table 6-2, Network Diagram Data for a Small Project.Allduration estimates or estimates...

David answered on Dec 22 2021
126 Votes
Assignment
a)
In the above diagram, Lines in dark represents the critical path.
b) All the poss
ible paths are-
    Paths
    Length
    1(2(3(6(8(9 or A(B(E(H(K
    2+2+2+2+2=10
    1(2(4(6(8(9 or A(C(F(H(K
    2+3+3+2+2=12
    1(2(5(7(8(9 or A(D(G(J(K
    2+4+6+1+2=15
    1(2(3(6(7(8(9 or A(B(E(I(J(K
    2+2+2+5+1+2=14
    1(2(4(6(7(8(9 or A(C(F(I(J(K
    2+3+3+5+1+2=16
c)
    Activity
    Initial Node
    Final Node
    Est. Duration...