Consider Table 6-2. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. (Note that you can easily change this table to create multiple exercises.) a....



Consider Table 6-2. All duration estimates or estimated times are in days, and the network


proceeds from Node 1 to Node 9. (Note that you can easily change this table to create


multiple exercises.)


a. Draw an AOA network diagram representing the project. Put the node numbers in


circles and draw arrows from node to node, labeling each arrow with the activity letter


and estimated time.


b. Identify all of the paths on the network diagram and note how long they are, using


Figure 6-8 as a guide for how to represent each path.


c. What is the critical path for this project and how long is it?


d. What is the shortest possible time needed to complete this project?



May 20, 2022
SOLUTION.PDF

Get Answer To This Question