Compute the followings: a. A project has a budget of $15M and scheduled for 1 year. It is assumed that the total budget will be spent equally each month. After 1 month the project manager finds that...


Compute the followings:
a. A project has a budget of $15M and scheduled for 1 year. It is assumed that the total budget will be spent
equally each month. After 1 month the project manager finds that only 7.5% of the work is finished and a
total of $1.5M spent. Find the following: Variances: CV, SV; Indices: CPI, SPI; Forecasting: EAC, ETC,
Time to completion.
b. In month 9, the following project information is available: Actual cost is $2000, Earned value is $2100 and
Planned cost is $2400. Compute the SV and CV for the project.
c. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560.
Compute the SV, CV and CPI for the project. What is your assessment of project on day 51?



Jun 05, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here