Compare the following two alternatives by the IRR method, given MARR of 6%/year. First find if they are feasible and then compare them with the incremental rate of return (AROR). Alt. Construction...


Compare the following two alternatives by the IRR method, given MARR of 6%/year. First find if they<br>are feasible and then compare them with the incremental rate of return (AROR).<br>Alt.<br>Construction cost $<br>Benefits $/yr Salvage $<br>Service Life (yrs)<br>A<br>410,000<br>55,000<br>20,000<br>11<br>B<br>250,000<br>35,000<br>10,000<br>11<br>

Extracted text: Compare the following two alternatives by the IRR method, given MARR of 6%/year. First find if they are feasible and then compare them with the incremental rate of return (AROR). Alt. Construction cost $ Benefits $/yr Salvage $ Service Life (yrs) A 410,000 55,000 20,000 11 B 250,000 35,000 10,000 11