Scott and Associates is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the...

Scott and Associates is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the various leader-client assignments differ in terms of projected completion times. The possible assignments and estimated completion times in days are given below. Find the optimal assignment of leaders to clients.Clients<br>Project Leader<br>2<br>3<br>Jack<br>10<br>16<br>32<br>Jane<br>14<br>22<br>40<br>John<br>22<br>24<br>34<br>Joanne<br>14<br>18<br>36<br>

Extracted text: Clients Project Leader 2 3 Jack 10 16 32 Jane 14 22 40 John 22 24 34 Joanne 14 18 36