Chrustuba Inc. is evaluating a new project that would cost $9 million at t = 0. There is a 50% chance that the project would be highly successful and generate annual after-tax cash flows of $6 million...

1 answer below »
Chrustuba Inc. is evaluating a new project that would cost $9 million at t = 0. There is a 50% chance that the project would be highly successful and generate annual after-tax cash flows of $6 million during Years 1, 2, and 3. However, there is a 50% chance that it would be less successful and would generate only $1 million for each of the 3 years. If the project is highly successful, it would open the door for another investment of $10 million at the end of Year 2, and this new investment could be sold for $20 million at the end of Year 3. Assuming a WACC of 8.75%, what is the project's expected NPV (in thousands) after taking this growth option into account?

Answered Same DayDec 24, 2021

Answer To: Chrustuba Inc. is evaluating a new project that would cost $9 million at t = 0. There is a 50%...

Robert answered on Dec 24 2021
137 Votes
Chrustuba Inc. is evaluating a new project that would cost $9 million at t = 0. There is a 50% chance that
the project would be highly successful and generate annual after-tax cash flows of $6 million during
Years 1, 2, and 3. However, there is a 50% chance that it would be less successful and would generate
only $1 million for each of the 3 years. If the project is highly successful, it would open the door for
another investment of $10 million at the end of Year 2, and this new investment...