Project work


BSB50215 Diploma of Business BSB51918 Diploma of Leadership and Management 10118NAT Diploma of Social Media Marketing BSB51415 Diploma of Project Management BSBPMG522 Undertake project work Task 2- Project Plan and Role Plays Candidate Instructions Purpose of this Assessment task This assessment task is designed to test your skills in undertaking project work as required by the unit BSBPMG522 Undertake project work. Your trainer/assessor will be assessing your work and provide you with constructive feedback on Canvas. This task will assess your skills to: · Define project · Develop project plan · Administer and monitor project · Finalise project · Review project. In this assessment you will analyse the provided case provided, undertake research in the topics presented, conduct 2 role-plays to demonstrate your skills and provide report to your Trainer. By successfully completing this Case Study you will provide the required performance evidence of your competence in undertaking project work. What are you required to do to undertake this Case Study? You should carefully read the provided Case Study; its additional documents provided on Canvas and undertake all questions. The task includes: (i) Analysing the case (ii) Undertaking required research (iii) Role playing and (iv) Reporting. To successfully undertake this assessment, you should be doing the following: · Read the provided Case Study couple of times and understand its requirements · Clarify the requirements with your trainer and assessor, if you are not sure · Research appropriate websites as directed by your trainer/assessor · Self-reflect and practice the 2 role-play before you record them and upload them on Canvas · Discuss with your trainer/assessor the contents of the report you will be presenting Context and conditions of undertaking the tasks? The prescribed tasks will be undertaken by you after carefully analysing the case scenarios. Your trainer/assessor will provide you a context to role-play the scenario. Your trainer will also provide you guidance on the websites to be researched. Your trainer/assessor may also set certain conditions under which you will perform the tasks required by this assessment. For example, your trainer may set a time limit to perform a task or, ask you to repeat a task or, ask you to give additional information about the performance by asking you some verbal questions or, they may prescribe you some new conditions to undertake certain tasks. Given your personal conditions, your trainer/assessor should also be able to make some reasonable adjustments in undertaking the tasks of this assessment. You should check with your trainer/assessor about the conditions under which the tasks should be completed, and the possible adjustment they can make in undertaking these tasks. What specific WHS requirements may be involved? This assessment will require you to be aware of the standard Workplace Health and Safety requirements e.g. Workplace Health and Safety Act and Workplace Health and Safety Legislation Your trainer/assessor will advise you on these and other legislative requirements. Tasks and frequency of performance Details of the tasks to be undertaken in this assessment are provided in the attached Case Study. The tasks listed in that document must be performed at least once. The role-play question should involve at least 2 team members. Getting Started The assessment may be re-attempted on two further occasions (maximum three attempts in total). All assessments must be resubmitted 3 days within receiving your unsatisfactory grade. You must clearly indicate “Re-submission” on your resubmitted work. You must complete all questions unassisted by the assessor or other personnel but may refer to reference material as may be needed. All questions must be answered satisfactorily for the assessment to be completed satisfactorily. For any assessment conducted that is incomplete, or without satisfactory performance, the assessment will need to be completed again after further training support. This may be simply to focus on question areas not achieved in the prior assessment. Submitting your assessment When you are ready to submit your assessments, upload the files in Canvas via the submission tab. It is important that you keep a copy of all electronic assessments submitted to Canvas. Please submit all assessment components. Word count In this assessment some of the questions include a word count. This is a guideline only, but your answers should not vary substantially (i.e. +/- 10%) from the word count provided. Microsoft Word includes a word count tool. Objective To test the required application skills in undertaking project work. Assessment Cover Sheet Candidate name: Trainer’s Name: Date Submitted: Candidate declaration: I declare that: · I have read and understood all the information provided in relation to the assessment requirements to complete this unit, the instructions and the purpose and processes of undertaking this assessment task · This assessment is my own work and where other’s works or ideas have been borrowed, I have appropriately referenced or acknowledged them · I understand that plagiarism is a serious offence that may lead to disciplinary action. Candidate signature: Task Description For this assessment you are required to undertake a straightforward project, which includes developing a project plan, administering and monitoring the project, finalising the project and reviewing the project to identify lessons learned for application in future projects. You must complete this assessment based on this stimulated organisation: Australian Hardware Store Case Study. You can access all their supporting documents by clicking here: http://australianhardware.simulations.australiantrainingproducts.com.au/ The intranet tab on this site will direct you to the relevant Australian hardware documents. A range of other documents are also within this intranet page and provide valuable background information about the operation of the business. Simulated Scenario – Australian Hardware Store You have recently been appointed as the Store Manager of the Australian Hardware Newcastle store. You and the COO (Chief Operating Officer) have discussed opportunities for you to make an impact and improvements in relation to how the Newcastle store operates. An area for improvement that has been previously identified by the Human Resources Manager is around developing policies and procedures for your store. You have noticed the Wollongong store has already implemented policies and procedures which have made a positive operational impact on the store. These policies and procedures only require minor amendments before they can be utilised in your store. As these policies and procedures will be new to staff, it will be essential communicate these changes, as well as to organise and provide training to all staff. To support you in developing and implementing the policies and procedures you have decided to develop a project plan, which will assist you with planning, monitoring and implementing your project. The project will include: · Amending Wollongong policies and procedures to suit the Newcastle store · Creating a Newcastle Store section on the company Intranet · Publishing policies and procedures to the Intranet · Communicating the policies and procedures to staff · Organising and providing training to all staff · Collecting feedback from staff on new policies and procedures The project will not include: · Collecting feedback from staff on training · Reviewing policies and procedures to identify whether further changes are required You have spoken to the Newcastle store about the project that they undertook, and they have advised you that you are likely to encounter competing priorities between HR and department managers as department managers do not like to take their staff away from serving customers in order to attend training. Part A - Project plan You are required to demonstrate your ability to create a project plan. The project plan must incorporate all the project plan specifications within the project plan template in Appendix 1. Your completed project plan will be approximately 1000 words in length. All completed reports and evidence must be uploaded into Canvas once completed. Part B – Project planning meeting Conduct a project planning meeting with at least two participants from your project team. You are required to record a 3–5-minute video file of the planning meeting. This recording must show an extract of you and your team discussing and determining the following: a) project objectives b) project purpose c) relationship to other projects d) scope of the project In your video file, you must include the following: ☐Evidence of participating in verbal discussions with your team using clear and appropriate language ☐Seeking information from your team by asking relevant questions from at least two (2) participants to encourage their input into project planning and to confirm their understanding of project objectives ☐Use of listening skills to demonstrate an understanding of the questions presented by your team (e.g. summarising questions and statements to confirm understanding) Part C - Clarification email Your project team identified an issue in relation to the scope of the project. They believe that feedback should be within the scope of the project. Draft an email to your manager seeking clarification as to whether this can be included in the project. At the same time, you will need to confirm with your manager whether this project is related to any other projects being undertaken by the organisation. Send To: From: Subject Part D: Project monitoring and implementation To demonstrate successful monitoring and implementation of the project, you must collect and prepare all reports and items of evidence specified for this part, using the provided templates Appendix 2. You will need to provide support for the project team with regards to their specific needs, ensuring the quality of the expected outcomes of the project and documented timelines. · Provide evidence of record-keeping in the form of at least three status reports for management (and other relevant stakeholders) at progress intervals of 25%, 50% and 75% during the project, using the templates provided. · Outline the support that team members may require over the life of the project. Provide an example of how you would provide that support regarding specific needs to ensure that the quality of the expected outcomes of the project and documented timelines are met. · Outline examples of when and how the communication and risk-management plans would be used in the project plan. Provide evidence of implementing communication and risk-management plans. · Summarise the deliverables the project plan needs to achieve and by what time they need to be achieved. · Outline three examples of what might cause the deliverables to not be achieved. Part E: Project finalisation Using the provided templates, complete the following project finalisation processes, including all specified sections and details. 1. Conduct a project review meeting with at least two participants from your project team. You are required to record a 3–5-minute audio/video file of the review meeting. This recording must show an extract of you and your team discussing and determining the following: 1. Whether objectives and deliverables were achieved 1. What worked well 1. Lessons learned In your video file, you must include the following: ☐Evidence of participating in verbal discussions with your team using clear and appropriate language ☐Seeking information from your team by asking relevant questions from at least two (2) participants
Answered Same DayNov 17, 2021BSBPMG522Training.Gov.Au

Answer To: BSB50215 Diploma of Business BSB51918 Diploma of Leadership and Management 10118NAT Diploma of...

Ishika answered on Nov 20 2021
154 Votes
Discussion
Part A - Project plan
Project title
Policy amendment and Related Changes at the Australian Hardware Newcastle store.
Project purpose
The purpose of the project is to amend the existing policies, open up a Newcastle Store section on the intranet and publish policy-related changes accordingly.
Relationship to other related projects
N/A
Project objectives
The project objectives should be aligned to the organisation’s strategic context, including:
· Mission
· Goals
· Objectives
· Operations
· Organisational structure
Ensure that you outline the organisation’s mission, goals, objectives and operations and how the project relates to them.
The mission of the project is to improve
the policies and procedures at the hardware store, thereby enhancing access for the employees regarding these policies and procedures.
The goals of the project is to ensure the employees have the access to policies and procedures and get notified of the changes made to the same.
The objectives of the project is to amend the policies and procedures, open up the intranet section, update the section accordingly, Train the staff and collect feedback from staff on new policies and procedures.
Scope (include key deliverables and documentation)
In scope: The new store needs policies and procedures that suit the needs best. The scope of this project is to amend those policies and procedures. Those policies and procedures would be then published in the store section that will be created on the company intranet. It will be communicated to the employees and training will be provided after which the feedback will be collected to improve the policies and procedures further.
Out of scope:
The staff who are still under training and the team that will review the existing policies and procedures are not included in the scope of the project.
Assumptions
The assumption of the project is that employees are trained in the existing policies and procedures and the intranet facility is provided by the New Castle Store.
Constraints
Communicating the policies and procedures to the new joiners or the staff who lacks technical knowledge would be a constraint. Ensuring that policies and procedures are followed right after implementation is another constraint. In addition to this, ensuring that the technical expert reviews and publishes the policies and procedures in a timely manner are another constraint.
Key People
Include a short explanation of how each of the key people contributed to the development of this project plan.
· Project client/owner:  Australian Hardware New Castle Store
· Project sponsor: The parent company that has opened up the New Castle Store is the sponsor of the project.
· Stakeholders: The people involved in the operations of the store, the parent company are the stakeholders of the project.
· Project Manager (you): XYZ
· Project team members: P, Q, R, S, T
Task list
List of all the tasks required for the project
    No.
    Task
    1
    Researching policies and procedures of Wollongong
    2
    Creating a section of a new castle store on the company intranet
    3
    Publishing the policies and procedures on the page
    4
    Communicating the policies and procedures to the Employees
    5
    Organizing and providing training to the employees
    6
    After training, collecting feedback from the employees on the new policies and procedures.
    
    
Work breakdown structure
A work breakdown structure (WBS) in project management is a tool used to define and group the project's work tasks in a way that helps organise and define the total work scope for the project.  The WBS is a dynamic tool and can be revised and updated as needed by the project manager.
    Level 1
    Level 2
    Level 3
    Task 1
Amending  policies and procedures
    
    
    
    Sub-task 1.1
Researching the policies and procedures
    
    
    
    Work item 1.1.1
Checking requirements
    
    
    Work item 1.1.2
Consulting with senior staff
    
    
    Work item 1.1.3
Creating a list of policy categories required
    
    Sub-task 1.2
Procedural Changes
    
    
    
    Work item 1.2.1
Reviewing traditional procedures
    
    
    Work item 1.2.2
Consulting with senior staff
    
    
    Work item 1.2.3
Creating a list of procedural categories required.
    Task 2
Intranet Maintenance and Training
    
    
    
    Sub-task 2.1
Intranet
    
    
    
    Work item 2.1.1
Creating a new castle store section on the company intranet
    
    
    Work item 2.1.2
Get approval for the draft and completing the list with legal guidance.
    
    
    Work item 2.1.3
Publishing on the intranet and continue updating it.
    
    Sub-task 2.2
Training
    
    
    
    Work item 2.2.1
Communicating the policies and procedures to the Employees during the training.
    
    
    Work item 2.2.2
Collecting feedback from them after training.
    Project Sponsor:
    Version:   1
    Project Client:
    
    Date:
    
    Project Manager:
    File Name: R&R.doc
    Page x of y
Gantt chart
To use a Gantt chart, list the activities and tasks in column A, select an appropriate time interval    days, weeks or months), allocate the dates to columns B onwards and plot the expected time duration (total time from start to completion) under the appropriate column by selecting shading from the cells.  When you wish to provide a status report, simply color or shade in black those items that are completed or estimate the percentage complete. This will give you an immediate visual representation as to whether you are on schedule. You can add extra columns for assignment of responsibilities etc. For small projects, a Gantt chart can be created as a spreadsheet.
    Activity/Task
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    12
    13
    14
    15
    Resource policies and procedures
    XX
    XX
    
    
    
    
    
    
    
    
    
    
    
    
    
    Review the activities in the store
    
    XX
    XX
    XX
    
    
    
    
    
    
    
    
    
    
    
    Draft the policies and procedures
    
    
    
    
    XX
    XX
    XX
    
    
    
    
    
    
    
    
    Consult with legal team for finalization
    
    
    
    
    
    
    
    XX
    XX
    
    
    
    
    
    
     Upload the policies on the company intranet
    
    
    
    
    
    
    
    
    XX
    XX
    
    
    
    
    
    Provide training to the staff
    
    
    
    
    
    
    
    
    
    
    XX
    XX
    XX
    XX
    
    Collect feedback after training
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    XX
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    Project Sponsor:
    Version:   1
    Project Client:
    
    Date:
    
    Project Manager:
    File Name: Gantt.doc
    Page x of y
Responsibilities and reporting schedule
Using the information, you generated in the work breakdown structure (WBS), update the schedule below.
    Item (Task)
    Milestone date
    Responsibility
    Communication method
    Amending the policies and procedures
     12/11/2020
    Store manager
     In-person
    Publishing the policies and procedures
    17 /11/2020
    IT team and Store manager
     Online
    Communicating the policies and procedures to the employees
    28/11/2020
    Store manager and COO
     In-person
    Collecting feedback from the staff
    30/11/2020
     Store manager
     In-person and online
Resource and cost...