At this point ignore any resource over allocations. Copy your PartAQ1.mpp schedule to PartAQ2.mpp.Chris Parsons asks you to allocate all three analysts to task “1.1 Analysis of original system functionality”. Assume that with the additional resources the task still requires “6 personweeks” (i.e. that there will be a reduction in duration as the work can be divided equally among the three resources).a) What is the new duration of task 1.1 and has this change impacted on the overall duration of the project? Explain. b) What is the additional cost in adding these extra resources to the project? Explain.Save PartAQ2.mpp. You will be required to submit this file as part of your assignment submission.