Answer No. 24 Using the Percentage of completion Method, the realized gross profit or loss for the year 2021 is: a. 822,500 b. -35,000 c. 840,000 d. -122,500 No. 16 (the other picture: Roman...



Answer



No. 24 Using the Percentage of completion Method, the realized gross profit or loss for the year 2021 is:


a. 822,500


b. -35,000


c. 840,000


d. -122,500



No. 16 (the other picture: Roman Construction Company)



The billings in excess of cost or the cost in excess of billings to be reported in the balance sheet as od December 31,2019


a. 20,000 excess of cost over billings


b. 20,000 excess of billings over cost


c. 900,000 excess of cost over billings


d. 900,000 excess of billings over cost


Provide a complete solution. Thank You


Chapter 8- Long Term Construction Contracts<br>Incurred cost of materials, labor and overhead used in the work, P2,400,000.<br>Paid costs of materials purchased but set aside for use in a future date for<br>this project, P200,000. These materials do not have any alternative use and<br>cannot be sold to other parties.<br>Paid and incurred rectification work no expected to be recovered, P260,000.<br>Incurred general and administrative costs that are not reimbursable,<br>P100,000.<br>Incurred selling costs, P60,000.<br>Incidental income from the sale of certain materiałs, P40,000. These specific<br>materials were sold since it was considered surplus from the early phase of<br>the construction.<br>The engineers determined that the original estimate of costs did not include<br>any expected warranty costs of P200,000.<br>23. Determine the profit for the first year.<br>P600,000<br>P220,000<br>a.<br>P840,000<br>C.<br>b.<br>P715,000<br>d.<br>On August 1, 2019, Panglao Construction Company obtain a contract to construct<br>a low rise building in Taguig City. The building was estimated to cost P17.5M and<br>is scheduled for completion on October 2021. The contract contains a penalty<br>clause to the effect that the other party is to deduct P35,000 from the contract price<br>for each week of delay. Completion was delayed for 5 weeks. Below are the data<br>pertaining to the construction period.<br>2019<br>2020<br>2021<br>Costs incurred<br>Estimated cots to complete<br>Progress Billings<br>P1,750,000<br>7,000,000<br>1,400,000<br>P1,085,000<br>P6,440,000<br>910,000<br>15,225,000<br>4,200,000<br>24. Using the percentage of completion method, the realized gross profit (loss( for<br>the 2021 is:<br>year<br>P822,500<br>b. (P35,000)<br>a.<br>P840,000<br>C.<br>d.<br>(P122,500)<br>

Extracted text: Chapter 8- Long Term Construction Contracts Incurred cost of materials, labor and overhead used in the work, P2,400,000. Paid costs of materials purchased but set aside for use in a future date for this project, P200,000. These materials do not have any alternative use and cannot be sold to other parties. Paid and incurred rectification work no expected to be recovered, P260,000. Incurred general and administrative costs that are not reimbursable, P100,000. Incurred selling costs, P60,000. Incidental income from the sale of certain materiałs, P40,000. These specific materials were sold since it was considered surplus from the early phase of the construction. The engineers determined that the original estimate of costs did not include any expected warranty costs of P200,000. 23. Determine the profit for the first year. P600,000 P220,000 a. P840,000 C. b. P715,000 d. On August 1, 2019, Panglao Construction Company obtain a contract to construct a low rise building in Taguig City. The building was estimated to cost P17.5M and is scheduled for completion on October 2021. The contract contains a penalty clause to the effect that the other party is to deduct P35,000 from the contract price for each week of delay. Completion was delayed for 5 weeks. Below are the data pertaining to the construction period. 2019 2020 2021 Costs incurred Estimated cots to complete Progress Billings P1,750,000 7,000,000 1,400,000 P1,085,000 P6,440,000 910,000 15,225,000 4,200,000 24. Using the percentage of completion method, the realized gross profit (loss( for the 2021 is: year P822,500 b. (P35,000) a. P840,000 C. d. (P122,500)
On March T, 2018, Roman Construction Company was contracted to construct a<br>warehouse building for Sunflower Manufacturing Company for total contract<br>price of P8,400,000. The following data are available for the 3 years:<br>12/31/19<br>P2,600,000<br>12/31/18<br>P3,200,000<br>ndenco<br>P3,200,000<br>12/31/20<br>P1,450,000<br>Contract Costs incurred<br>during the year<br>Est. costs to complete at<br>12/31<br>Progress billings each year<br>P1,450,000<br>PO<br>P3,200,000<br>P3,500,000 P1,700,000<br>Roman Construction Company uses the percentage of completion method for<br>accounting for long term contracts.<br>

Extracted text: On March T, 2018, Roman Construction Company was contracted to construct a warehouse building for Sunflower Manufacturing Company for total contract price of P8,400,000. The following data are available for the 3 years: 12/31/19 P2,600,000 12/31/18 P3,200,000 ndenco P3,200,000 12/31/20 P1,450,000 Contract Costs incurred during the year Est. costs to complete at 12/31 Progress billings each year P1,450,000 PO P3,200,000 P3,500,000 P1,700,000 Roman Construction Company uses the percentage of completion method for accounting for long term contracts.
Jun 11, 2022
SOLUTION.PDF

Get Answer To This Question

Submit New Assignment

Copy and Paste Your Assignment Here