An important problem in manufacturing is the assembly line balancing problem. When setting up a manufacturing line, activities must be assigned to workstations. The maximum time spent at a workstation is called the cycle time. Minimizing the cycle time translates to maximizing the number of items that can be produced each hour. Here is a typical assembly line balancing problem that can be solved with the Evolutionary Solver. Manufacture of a product consists of 10 activities (A–J) that require the times (in seconds) in the file P08_41.xlsx to complete. Certain activities must be completed before others. These precedence relations are also given in the file P08_41.xlsx. For example, activity A cannot be performed on a higher numbered workstation than activity B. Use Evolutionary Solver to determine an assignment of activities to workstations that minimizes the total cycle time.
Already registered? Login
Not Account? Sign up
Enter your email address to reset your password
Back to Login? Click here