An earned value report will show a project manager: A.The Slippages in time against planned measures. B. The budgeted value of work performed. C.How much money has been spent so far on the project. D....




An earned value report will show a project manager:

A.The Slippages in time against planned measures.



B. The budgeted value of work performed.




C.How much money has been spent so far on the project.




D. Slippages in performance measures for the work product.