all of the following reasons might lead to a contract termination for default except problems associated with the project schedule changing customer priorities a loss of confidence in the contractor...




all of the following reasons might lead to a contract termination for default except



  • problems associated with the project schedule

  • changing customer priorities

  • a loss of confidence in the contractor performing the project

  • problems associated with the project cost


closure of a project generally entails all of the following activities except:



  • ensuring all of the work has been accomplished

  • ensuring all resources have been reassigned

  • ensuring all documentation is complete

  • updating the .project management plan


all of the following describes benefits associated with celebrating the completion of a project accept:



  • celebrations can persuade team members to do just a bit more than they might otherwise

  • celebrations provide an opportunity to recognize team members efforts

  • celebrations mark transition points as people leave one project for another'

  • celebrations are held in conjunction with team performance reviews


a project team attempting to close a project should review each of the following to ensure the customer is satisfied with the project work?



  • the project charter

  • the customer feedback and scope verification

  • the communication plan

  • the project organizational chart


A project team attempting to close a project should review all of the following documents to ensure that everything promised was delivered



  • the project charter

  • the stakeholders registration

  • the work breakdown structure

  • the project schedule