All of the following are true regarding the Monitor and Control Project Work Process except which one? This process reports on and compares actual project results. This process monitors and controls...




All of the following are true regarding the Monitor and Control Project Work Process except which one?




  • This process reports on and compares actual project results.


  • This process monitors and controls project work from Initiating through the Monitor and Control process group.


  • This process monitors and approves change requests.


  • This process analyzes performance data and recommends preventive or corrective actions.



  • 2

  • Which of the following processes must be integrated and coordinated during the Control Procurements process?


  • Monitor Communications, Control Procurements, Control Quality, Perform Integrated Change Control, and Control Risks


  • Direct and Manage Project Work, Monitor Communications, and Perform Integrated Change

  • Control


  • Plan Procurements, Monitor Communications, Control Quality, and Perform Integrated Change Control


  • Direct and Manage Project Work, Control Quality, Perform Integrated Change Control, and Control Risks



  • 3

  • Monitor Communications involves evaluating and controlling the impact messages may carry and delivering the right message to the right people at the right time. This process is also about making certain the project information needs of the stakeholders are met. Work performance information is one of the primary outputs of this process. All of the following are true regarding work performance information except which one?


  • This information is used to analyze information such as the status of deliverables.


  • Forecasts of ETC might be reported in this output.


  • This might take the form of status reports, memos, or updates.


  • The status of change requests might be reported in this output.



  • 4

  • Corrective action is from a change request. Change requests (including approved change requests) are outputs of which process group and inputs to which process group respectively?


  • Outputs of Planning, Executing, and Monitoring and Controlling, and inputs to Executing and to Monitoring and Controlling


  • Outputs of Executing and Monitoring and Controlling, and inputs to Monitoring and Controlling


  • Outputs of Executing and Monitoring and Controlling, and inputs to Executing and Monitoring and Controlling


  • Outputs of Planning and Executing, and inputs to Executing and Monitoring and Controlling



  • 5

  • Which of the following groups is responsible for approving or denying change requests after reviewing?


  • CRB


  • CCB


  • CRC


  • CCC