Ajeet Construction Ltd is planning to take a project which initial cash outflow is XXXXXXXXXXThe expected cash inflows from this are tk 40000, tk25,000, tk 20000,tk 35,000, & tk.35000. Calculate...


Ajeet Construction Ltd is planning to take a project which initial cash outflow is 100000.The


expected cash inflows from this are tk 40000, tk25,000, tk 20000,tk 35,000, & tk.35000.


Calculate the NPV & IRR of this project, when rate of cost of capital is 15%.