Activity No. Activity Duration(weeks) Immediate Predecessors 1 Collect requirements 3 None Analyze processes 2 1 3 Analyze data 2 2 4 Design processes 6. 2 Design data 3 3 6. Design screens 2 3, 4...


A project has been defined to contain the following list of activities along with their required times for completion.


A-Draw activity bar chart


B-Draw Staff allocation table (consider the staff name by yourself, hire 6 staff members, 1 for requirement collection, 1 for analysis activities, 1 for design activities, 1 for program, 1 for test & document and 1 for software installation)


Activity No.<br>Activity<br>Duration(weeks)<br>Immediate Predecessors<br>1<br>Collect requirements<br>3<br>None<br>Analyze processes<br>2<br>1<br>3<br>Analyze data<br>2<br>2<br>4<br>Design processes<br>6.<br>2<br>Design data<br>3<br>3<br>6.<br>Design screens<br>2<br>3, 4<br>Design reports<br>4<br>4, 5<br>8<br>Program<br>5<br>6, 7<br>Test and Document<br>7<br>7<br>10<br>Install<br>8, 9<br>

Extracted text: Activity No. Activity Duration(weeks) Immediate Predecessors 1 Collect requirements 3 None Analyze processes 2 1 3 Analyze data 2 2 4 Design processes 6. 2 Design data 3 3 6. Design screens 2 3, 4 Design reports 4 4, 5 8 Program 5 6, 7 Test and Document 7 7 10 Install 8, 9