Homework problem 8.2


Make critical network diagram and draw the cpm or pert chart.


Calculate the total float free float indepent float


Activity Immediate Predecessors Duration<br>A<br>5<br>В<br>20<br>C<br>A<br>22<br>D<br>A<br>10<br>E<br>В<br>13<br>F<br>В<br>20<br>G<br>D,E<br>20<br>H<br>D,E<br>15<br>D,E<br>15<br>J<br>C,G<br>10<br>K<br>F,I<br>20<br>-<br>

Extracted text: Activity Immediate Predecessors Duration A 5 В 20 C A 22 D A 10 E В 13 F В 20 G D,E 20 H D,E 15 D,E 15 J C,G 10 K F,I 20 -