Activity
Immediate Predecessor
Optimistic Time
Most Likely Time
Pessimistic time
Time Expected
1
-
6
10
14
2
0
3
16
20
30
21
4
5
7
13
4,6
8
9
3,7
11
5,8
10,11
1. What are the two critical paths?
2. What is the duration?
3. What is the EF (early finish) of 7?
4. What is the LS (late start) o 4?