Activity Dependency Optimistic Most likely Pessimistic A 15 6. 13 4 5 C A 2 3 14 x= (last digit of your roll no. +4) 3 D x-1 x+2 roll no:4506 E 1 4 F 18 10 15 E,F 12 3 4 C,D 2 2.5 1. By using three...


Activity Dependency<br>Optimistic<br>Most likely<br>Pessimistic<br>A<br>15<br>6.<br>13<br>4<br>5<br>C<br>A<br>2<br>3<br>14<br>x= (last digit of<br>your roll no. +4)<br>3<br>D<br>x-1<br>x+2<br>roll no:4506<br>E<br>1<br>4<br>F<br>18<br>10<br>15<br>E,F<br>12<br>3<br>4<br>C,D<br>2<br>2.5<br>1. By using three estimates for each activity, find:<br>1.1. Estimated time't,

Extracted text: Activity Dependency Optimistic Most likely Pessimistic A 15 6. 13 4 5 C A 2 3 14 x= (last digit of your roll no. +4) 3 D x-1 x+2 roll no:4506 E 1 4 F 18 10 15 E,F 12 3 4 C,D 2 2.5 1. By using three estimates for each activity, find: 1.1. Estimated time't," 1.2. Activity standard deviation's' 2. Draw PERT network after calculating the events' estimated times and standard deviations.

Jun 11, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here