For a particular project, consider following list of Activities, their duration in Days and their Predecessoractivities.
By using network schedule technique, draw a Network Diagram of above enlisted activities.Find Critical Path , earliest start, earliest finish , latest start and latest finish from NetworkDiagram. 2 – Marks