Extracted text: Activity A has 6-days duration (ESD A is day 5), and activty B has 4-days duration, the relation is " activity B must start 2 days before start of activity A, LFD of project is 11 days, then Select one: O a. LSD B= 3 , and LFD B= 7 Ob. LSD B= 3, and LFD B= 11 C. LSD B=7, and LFD B= 11 O d. LSD B= 0, and LFD B=11
Extracted text: Activity A has 6-days duration, and activty B has 3-days duration, the relation is " activity B must finish at least 5 days after start of activity A, then Select one: Oa ESD B-1, and LSD B 1 b ESD B 0, and LSD B3 OG ESD B 0, and LSD B 1 Od ESD1 0, and LSD B 0