Given the table, provide the network diagram. Determine EarlyStart and Early Finish of the project and indicate them in the network. Activity a b Immediate t Predecessor (days) A 1 3 3 В 0.5 1 1.5 A 1...


Given the table, provide the
network diagram. Determine
EarlyStart andEarly Finish


of the project and indicate them in the network.



Activity<br>a<br>b<br>Immediate<br>t<br>Predecessor<br>(days)<br>A<br>1<br>3<br>3<br>В<br>0.5<br>1<br>1.5<br>A<br>1<br>4<br>6.<br>8<br>A<br>6<br>7<br>В<br>9.33<br>E<br>1<br>3<br>2.66<br>F<br>6.<br>9.<br>12<br>D<br>9<br>G<br>7<br>10<br>13<br>С, F<br>10<br>H<br>1<br>3<br>5<br>C<br>3<br>4<br>6.<br>H<br>4<br>J<br>1<br>2<br>3<br>E, G, I<br>2<br>K<br>0.5<br>1<br>1.5<br>H<br>1<br>E<br>

Extracted text: Activity a b Immediate t Predecessor (days) A 1 3 3 В 0.5 1 1.5 A 1 4 6. 8 A 6 7 В 9.33 E 1 3 2.66 F 6. 9. 12 D 9 G 7 10 13 С, F 10 H 1 3 5 C 3 4 6. H 4 J 1 2 3 E, G, I 2 K 0.5 1 1.5 H 1 E

Jun 09, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here