Given the table, provide thenetwork diagram. DetermineEarlyStart andEarly Finishof the project and indicate them in the network.
Extracted text: Activity a b Immediate t Predecessor (days) A 1 3 3 В 0.5 1 1.5 A 1 4 6. 8 A 6 7 В 9.33 E 1 3 2.66 F 6. 9. 12 D 9 G 7 10 13 С, F 10 H 1 3 5 C 3 4 6. H 4 J 1 2 3 E, G, I 2 K 0.5 1 1.5 H 1 E