A sponsor that is part of TOP has asked you to make structural changes to your project so that the sponsor’s company logo can displayed more prominently. This will delay your project a bit and cause a...

A sponsor that is part of TOP has asked you to make structural changes to your project so that the sponsor’s company logo can displayed more prominently. This will delay your project a bit and cause a cost overrun. The OCOG tells you to make the changes but within the existing cost baseline. What should you do next, and whom should you discuss this with?