A software project plan shown in Table 10.22 includes 30 tasks. It was estimated that 300 person-months will be needed to complete the project. At a given time T, 9 tasks were supposed to be complete,...

A software project plan shown in Table 10.22 includes 30 tasks. It was estimated that 300 person-months will be needed to complete the project. At a given time T, 9 tasks were supposed to be complete, according to the original plan. Table 10.22 shows that only 6 tasks were completed at time T. Compute the BCWP, BCWS, SPI, CPI, CV, SV, VAC, and EAC at time T.