A proposed new project has projected sales of $222,000, costs of $96,500, and depreciation of $26,100. The tax rate is 24 percent. Calculate operating cash flow using the four different approaches....









A proposed new project has projected sales of $222,000, costs of $96,500, and depreciation of $26,100. The tax rate is 24 percent. Calculate operating cash flow using the four different approaches.(Do not round intermediate calculations.)



EBIT+Deprectiation-taxes


Top-down


Tax Shield


Bottom-up