A project's duration can be reduced by a) shortening the duration of critical path tasks b) adding tasks to the critical path c) adding shorter routes around the critical path d) completing the...




A project's duration can be reduced by
a) shortening the duration of critical path tasks


b) adding tasks to the critical path


c) adding shorter routes around the critical path


d) completing the backward pass first