A project that provides annual cash flows of $2,250 for 9 years costs $9,300 today. a) At a required return of 10 percent, what is the NPV of the project? b) At a required return of 26 percent, what...


A project that provides annual cash flows of $2,250 for 9 years costs $9,300 today.<br>a) At a required return of 10 percent, what is the NPV of the project?<br>b) At a required return of 26 percent, what is the NVP of the project?<br>c) At what discount rate would you be indifferent between accepting the project and rejecting it?<br>

Extracted text: A project that provides annual cash flows of $2,250 for 9 years costs $9,300 today. a) At a required return of 10 percent, what is the NPV of the project? b) At a required return of 26 percent, what is the NVP of the project? c) At what discount rate would you be indifferent between accepting the project and rejecting it?