A project is estimated to cost P110,000, last 8 years and have a P15,000 salvage value. The annual gross income is expected to average P24,000 and annual expenses, excluding depreciation, will total...


A project is estimated to cost P110,000, last 8 years and have a P15,000 salvage
value. The annual gross income is expected to average P24,000 and annual
expenses, excluding depreciation, will total P6,000. If capital is earning 10% before
income taxes, determine if this is a desirable investment using Payback Period in years: