A project has the following activities; the activities and precedence relationships are given in below network diagram. Consider the Duration of activities in Days. 1) Find critical path 2) Find the...


A project has the following activities; the activities and precedence relationships are given in below network diagram. Consider the<br>Duration of activities in Days.<br>1)<br>Find critical path<br>2)<br>Find the expected project completion time<br>B<br>C (9)<br>(10)<br>G (9)<br>H(6)<br>A (3)<br>D (8)<br>F (9)<br>E (6)<br>hp<br>

Extracted text: A project has the following activities; the activities and precedence relationships are given in below network diagram. Consider the Duration of activities in Days. 1) Find critical path 2) Find the expected project completion time B C (9) (10) G (9) H(6) A (3) D (8) F (9) E (6) hp