A management consultancy recovers overheads on the basis of chargeable consulting hours. Budgeted overheads were $615,000 and actual consulting hours were 32,150. Overheads were under-recovered by...


A management consultancy recovers overheads on the basis of chargeable consulting hours. Budgeted


overheads were $615,000 and actual consulting hours were 32,150. Overheads were under-recovered


by $35,000.


If actual overheads were $694,075, what was the budgeted overhead absorption rate per hour?